Cabell County Schools - Dedicated to the Success of Every Student

Click to return to Construction Updates

HEMS UPDATE AS OF June 22, 2012

*             25 % OF FOOTERS HAVE BEEN POURED
*             THE GYMNASIUM SLABS AND CURVED CORRIDOR HAVE  BEEN P0URED
*             SAMPLE POLISHED FLOOR SLAB WITH COLOR HAS BEEN COMPLETED (NOTE THE COLORS IN THE PICTURE) MORE COLORS ARE TO COME
*             THE FLOOR GRINDING AND POLISHING IS BEING DEMONSTRATED AND MONITORED BY ZMM CONSULTANT
*             STRUCTURAL STEEL HAS BEEN STARTED IN THE CORNER OF THE GYMNASIUM
*             BOND BEAMS ARE BEING POURED IN THE WALLS FOR STRENGTH
*             THE EASTERN WING OF CLASSROOM FLOORS ARE BEING READIED FOR SLAB POURS THAT SHOULD TAKE PLACE IN ABOOUT TEN DAYS     
*             THE PROJECT STUDY FOR THE STOP LIGHT ON RT. 60 DID NOT QUALIFY FOR A LIGHT 
*             NORWAY PROPERTY (HOUSE) HAS BEEN PURCHASED AND BEEN CLEARED (AREA WHERE SIGN IS)
*             COMPLETING FOOTERS IN AREA C
*             COORIDOR WALS ARE GOING UP
*             ELECTRICAL CONDUIT HAS BEEN INSTALLED FOR MAIN DISTRIBUTION PANEL
*             WALL BRACES HAVE BEEN INSTALLED ON INTERIOR WALLS AS PEER OSHA STANDARDS (SEE PICTURE)
*             PROJECT IS CURRENTLY ON SCHEDULE

 

Click to return to Construction Updates